PROJECT PHASES
-
Current Phase: Zoning Application
ZONING APPLICATION WITHDRAWN: 11/04/2024
30 DAY STAFF REVIEW: Completed 9/8/2024
CONTRACT ZONE AND ZONING MAP AMENDMENT APPLICATIONS: Filed 7/31/2024
PRE-APPLICATION MEETING: Completed 2/7/2023
Yard South’s zoning application brings the site into alignment with the City’s 2012 Comprehensive Plan. The Comp Plan envisions this underutilized industrial land as a place for people to live, work, and enjoy the waterfront.
-
Future Phase: Subdivision
STATUS: NOT SUBMITTED
The Subdivision application will divide Yard South into development parcels and address infrastructure design and capacity.
-
Future Phase: Site Plan
STATUS : NOT SUBMITTED
The Site Plan application shows the physical site design, vehicular and pedestrian access, and the interrelationship of these elements.