Yard South Phases and Site History

PROJECT PHASES

  • Current Phase: Zoning Application

    ZONING APPLICATION WITHDRAWN: 11/04/2024

    30 DAY STAFF REVIEW: Completed 9/8/2024

    CONTRACT ZONE AND ZONING MAP AMENDMENT APPLICATIONS: Filed 7/31/2024

    PRE-APPLICATION MEETING: Completed 2/7/2023

    Yard South’s zoning application brings the site into alignment with the City’s 2012 Comprehensive Plan. The Comp Plan envisions this underutilized industrial land as a place for people to live, work, and enjoy the waterfront.

  • Future Phase: Subdivision

    STATUS: NOT SUBMITTED

    The Subdivision application will divide Yard South into development parcels and address infrastructure design and capacity.

  • Future Phase: Site Plan

    STATUS : NOT SUBMITTED

    The Site Plan application shows the physical site design, vehicular and pedestrian access, and the interrelationship of these elements.